Unique Meghnaghat Power achieves financial close for $463m foreign loans, gets first disbursement of $360m 

News Desk | banglanews24.com
Update: 2024-01-20 17:32:38
Unique Meghnaghat Power achieves financial close for $463m foreign loans, gets first disbursement of $360m 

Unique Meghnaghat Power Limited (UMPL) has recently achieved financial close for the USD 463 million long-term project financing from foreign lenders on 13 December 2023 and got the first disbursement of USD 360 million on 18 December 2023.

UMPL has constructed 584 MW combined cycle gas fired power plant project at Sonargaon, Narayanganj, Bangladesh. UMPL is a consortium of Strategic Finance Limited (SFL), Unique Hotels & Resorts PLC (UHRL) and Nebras Power Investment Management B.V. (Nebras). The construction and commissioning of the Project has already been completed and the project is ready for commercial operation.

The estimated project cost is USD 612 million which is being financed at 75:25 debt-equity ratio. The debt portion is being financed through multi-sourced financing package including an ECA covered tranche from Standard Chartered Bank (SCB) with cover from Swiss Export Risk Insurance (SERV) as well as three DFI tranches, from Asian Infrastructure Investment Bank (AIIB), Deutsche Investitions-und Entwicklungsgesellschaft (DEG) and OPEC Fund for International Development (OFID). Out of USD 360 million first disbursement, SCB as ECA backed lenders disbursed USD 240.24 million and AIIB, DEG & OFID as DFI lenders disbursed USD 119.76 million.

This is the largest IPP project financing and private infrastructure project financing to have closed in the past few years in Bangladesh. This is particularly remarkable given this has been achieved amid stressed FX situation in Bangladesh and financial volatility in the global market due to post Covid pandemic recovery and global political turmoil.

Chowdhury Nafeez Sarafat, Managing Director of UMPL said that this financing manifests the confidence of lead global Development Financing Institutions (DFIs) and Banks on the economic development of Bangladesh. Financing closing of USD 463 million foreign loan has opened the avenue for the future investment in Bangladesh for the similar set of foreign lenders. He also said that UMPL has implemented the Project with the most efficient gas turbine in South Asia i.e., GE 9HA which has the highest efficiency of more than 62% at site condition. In the time of scarcity of natural gas, the commercial operation of this project will ensure the optimum utilization of gas. This financing will make this project a world-class infrastructure project, providing cleaner, reliable, and affordable electricity to the people of Bangladesh.

Anupam Hayat, Chief Financial Officer of UMPL said that we are very happy to announce the Financial Close and first disbursement of USD 463 million foreign loan. Given the Covid-19 and Russia-Ukraine war impacts, it was very challenging to achieve the Financial Close. I would like to thank lenders, sponsors, regulators, management team and all the advisors for their cooperations for achieving the Financial Close during these difficult times.

BDST: 1732 HRS, JAN 20, 2024